Earlier this month, the Land Transport Authority shared that construction for the Cross Island Line (CRL) has commenced, with the first phase slated to finish by 2030.
On Monday (30 Jan), LTA announced that they’ve finished appointing contractors for all four stations along the Punggol Extention of the CRL — the extension branches from the main line via Pasir Ris Station.
With the contractors appointed, construction works for the four stations are slated to start in Q2 2023.
In a press release on Monday (30 Jan), LTA announced that they’d awarded the contract for the design and construction of Elias Station, as well as the tunnels under Cross-Island Line-Punggol Extension (CPe) to Chip Eng Seng Contractors Pte Ltd.
LTA said the CPe Elias Station would be located along Pasir Ris Drive 3 at an approximate depth of 40m. Commuters can also access the station through any of its five entrances.
Construction works for Elias Station and the tunnels are expected to start in Q2 2023, with a target of commencing service in 2032.
With this, LTA said they’d appointed contractors for all four stations along the CPe.
Comprising Pasir Ris, Elias, Riviera, and Punggol stations, the 7.3KM CPe will better connect Easties to others in the northeastern region.
This includes halving the travel time needed for commuters to get between Elias and Hougang — from 40 minutes to 20 minutes.
Interestingly, three of the four stations are interchanges, providing even greater ‘reach’ to residents staying around these ‘nodes’.
LTA estimate that more than 40,000 households are expected to benefit from the CPe when it’s completed.
Though it will be about a decade before the CRL commences service, commuters can still look forward to further convenience of travelling upon completion.
Know someone who’d benefit greatly from the upcoming CRL? Tag them in the comments to keep them informed about the progress.
Have news you must share? Get in touch with us via email at hello@mustsharenews.com.
Featured image adapted from Land Transport Authority.
A record of more than 553,000 travellers crossed both checkpoints on 13 Dec.
There has been no year-end Covid-19 wave, as had been expected.
The beef was imported without a veterinary health certificate and halal certification.
One fan started queueing as early as 7am.
The company made the change after parents said they wanted to make sure their gifts…
An incredible twist of fortune for the police -- and a stroke of bad luck…