TEL Stations To Close At 9pm Daily Till Year-End, More Testing For Stage 2 Needed

TEL Stations To Close At 9pm Daily Till Year-End, It’s The 2nd Extension So Far

If you’re a Woodlands resident, you would have known that the 3 Thomson-East Coast Line (TEL) stations in the estate had reduced their operating hours since 20 Jul.

Source

The measure was supposed to have lasted till 30 Aug, but was extended till 1 Nov.

Now, it’s been extended again till the end of the year, said the Land Transport Authority (LTA) on Facebook.

Source

TEL stations will close at 9pm every day

In a Facebook post on Thursday (29 Oct), the LTA said the TEL stations will close at 9pm every day.

They will also open later at 6.30am on Saturday and Sunday.

This will be in effect up till 31 Dec, it added.

Source

More testing for Stage 2 of TEL

The reduction in operating hours will facilitate additional testing of trains and systems.

 

It’s needed as Stage 2 of the TEL is due to open at an unconfirmed date next year.

It comprises 6 more stations, from Springleaf to Caldecott.

The current TEL that’s in operation so far comprises just 3 stations:

  • Woodlands North Station
  • Woodlands Station
  • Woodlands South Station

Source

No shuttle buses provided

As there will be no shuttle buses provided, residents who’ve been bearing with the reduced operating hours should by now have figured out alternate modes of transport.

SMRT has advised commuters travelling within Woodlands to rely on existing bus services like 169, 856, 901 and 901M.

SMRT has also advised commuters to transfer to the North-South Line (NSL) at Woodlands NSL station, which will be open as normal, if they wish to continue their journey via MRT.

Source

Looking forward to Stage 2

While the continued early closure of the TEL may cause inconvenience to Woodlands residents, the added engineering hours should be put to good use.

They’re necessary to facilitate the opening of the long-awaited Stage 2, whose opening was delayed from end-2020 to early 2021 due to the temporary suspension of contraction works due to the Covid-19 pandemic.

The Government is committed to continuing the project, though, and we can look forward to Stage 2 connecting northern Singapore very soon.

Have news you must share? Get in touch with us via email at hello@mustsharenews.com

Featured image adapted from Google Maps.

Jeremy Lee

Analog person making do with a digital world.

Recent Posts

Serangoon HDB flat sold for S$1.208M, becomes most expensive unit in the estate

Prices in Serangoon are rapidly escalating, with a 7.01% increase in the average price this…

29 Mar 2024, 3:29 pm

Scissors penetrate Thai girl’s skull after 4-year-old brother throws them to imitate TV show

The depth of penetration was 2.54cm, or an inch. 

29 Mar 2024, 2:25 pm

Mother of US toddler who died after being left alone for 10 days gets life imprisonment

The judge said she committed "the ultimate betrayal".

29 Mar 2024, 12:25 pm

Expats find S’pore too costly to live in: Many are feeling the pinch & want to leave

Despite the country being an attractive place to live in, elevated costs are causing many…

29 Mar 2024, 10:20 am

S’pore checkpoints see massive jams before Good Friday long weekend with more than 4 hours’ wait

The queue at Tuas was four hours and 40 minutes long at 11.16pm.

29 Mar 2024, 7:23 am